HPE GreenLake Solutions (HPE2-B07) Certification Sample Questions

HPE HPE2-B07 VCE, GreenLake Solutions Dumps, HPE2-B07 PDF, HPE2-B07 Dumps, GreenLake Solutions VCE, HPE GreenLake Solutions PDFGetting knowledge of the Hewlett Packard Enterprise HPE2-B07 exam structure and question format is vital in preparing for the HPE GreenLake Solutions certification exam. Our HPE GreenLake Solutions sample questions offer you information regarding the question types and level of difficulty you will face in the real exam. The benefit of using these Hewlett Packard Enterprise HPE2-B07 sample questions is that you will get to check your preparation level or enhance your knowledge by learning the unknown questions. You will also get a clear idea of the exam environment and exam pattern you will face in the actual exam with the HPE GreenLake Solutions Sample Practice Test. Therefore, solve the HPE GreenLake Solutions sample questions to stay one step forward in grabbing the HPE Solution Certified - HPE GreenLake credential.

These Hewlett Packard Enterprise HPE2-B07 sample questions are simple and basic questions similar to the actual HPE GreenLake Solutions questions. If you want to evaluate your preparation level, we suggest taking our HPE GreenLake Solutions Premium Practice Test. You might face difficulties while solving the real-exam-like questions. But, you can work hard and build your confidence on the syllabus topics through unlimited practice attempts.

Hewlett Packard Enterprise HPE2-B07 Sample Questions:

01. For six months in a row, a customer's metered usage has run well above its reserved capacity, and the customer now complains that its bills are hard to predict.
What should the partner recommend?
a)
Increase the buffer capacity to make the metered charges predictable
b) Raise the reserve through a change order to cover the new steady usage
c) Leave the agreement unchanged and advise the customer to use less capacity each month
d) Start a new deal for the extra usage and keep it separate from the existing agreement
 
02. Partway through its term, an HPE GreenLake customer asks the partner to lower its reserved capacity because a project was cancelled.
How should the partner handle the request?
a)
 
Promise the reduction at once to protect the relationship, and settle the terms with HPE later
b) Tell the customer the reserve will drop on its own to the new usage level from the next month
c) 
Raise it as a change order and confirm with HPE what the agreement allows
d) Open a new quote and agreement so the customer starts over at a lower reserve
 
03. An HPE GreenLake deal involves the customer, HPE, HPEFS and the partner. Under this deal's structure, the partner will deliver its own migration services under a direct agreement with the customer.
Which parties sign the SOW for those migration services?
a)
The customer and the partner
b) HPEFS and the customer
c) HPE Services and the partner
d) Every party in the GreenLake deal
 
04. How should delivery of a newly signed HPE GreenLake solution begin?
a)
With a new business case, so that the customer can confirm the value before delivery starts
b) With the first change order, so that the scope can be adjusted before any work is done
c) With the partner's installers and HPE on site before any plan has been agreed
d) With a kickoff that aligns the customer, partner and HPE on schedule and responsibilities
 
05. A customer will move a critical vendor application onto new HPE GreenLake infrastructure. The application vendor supports only certain operating systems and virtualization platforms.
What should the partner confirm during design?
a)
That the application can be quoted through ASQ with the infrastructure
b) That the proposed platform is one the application vendor supports
c) That the reserved capacity covers the application's license count
d) That HPEFS has approved the application for the financing agreement
 
06. While preparing the order for an HPE GreenLake solution, the partner notices that the configuration in the order does not match the configuration in the signed agreement.
What should the partner do?
a)
Resolve the difference and match the order to the signed agreement
b) Place the order as it is and fix the difference with a change order later
c) Ask the delivery team to choose the configuration at installation time
d) Place the order using whichever configuration costs the customer less
 
07. Halfway through delivery of an HPE GreenLake solution, the partner realizes that its own migration work will finish two weeks later than the agreed plan.
What should the partner do?
a)
Keep working quietly and explain the delay once the work is finished
b) Raise a change order that moves the date and adds cost for the customer
c) 
Hand the remaining migration work to HPE so the original date still holds
d) Tell the customer and HPE promptly, and agree a revised plan with them
 
08. Two customers are buying similar HPE GreenLake infrastructure. Customer A has a small, stretched IT team that wants to stop doing day-to-day operations. Customer B has a strong operations team that wants to keep running its environment.
How should the designs differ?
a)
Both designs should include the same managed services and operations support
b) Customer B's design should include managed services, since a strong team can supervise them
c) Customer A's design should include managed services, while Customer B runs its own
d) Neither design should include managed services, since services are added by change order
 
09. During a services workshop, a customer assumes the partner's GreenLake SOW also covers migrating a legacy application that nobody has discussed.
Which part of the SOW best prevents this kind of misunderstanding?
a)
A detailed list of the hardware to be installed
b) 
A clear statement of what is out of scope
c) The reserved capacity and the metered usage rates
d) The quoting route that the mapbook identified
 
10. In a customer's design, an application on HPE GreenLake in its data center will exchange large volumes of data with services it keeps in a public cloud.
What should the design take into account?
a)
Network bandwidth and latency between the data center and the public cloud
b) Buffer capacity on site, which carries the traffic to the public cloud
c) The quoting route for the public cloud services the customer keeps
d) The reserved capacity level, which sets the link speed to the cloud

Answers:

Question: 01
Answer: b
Question: 02
Answer: c
Question: 03
Answer: a
Question: 04
Answer: d
Question: 05
Answer: b
Question: 06
Answer: a
Question: 07
Answer: d
Question: 08
Answer: c
Question: 09
Answer: b
Question: 10
Answer: a